Building a pool on a sloped lot in Central Texas

Three things decide a pool on a slope: where the shell sits on the grade, what holds up the downhill side, and where the stormwater goes.

Trinity Pool Construction5 min read
Rebar and wood forms for a pool with a raised spa

Building a pool on a sloped lot in Central Texas is usually possible, and three things decide how it goes: where the shell sits on the grade, what holds up the downhill side, and where the stormwater goes. All three get settled on paper before the dig.

Trinity Pool Construction designs custom gunite pools for Hill Country yards that fall away from the house.

Can you build a pool on a sloped lot?

Yes. A gunite pool suits a sloped lot because the shell is formed on that piece of ground instead of delivered whole. Our post on what gunite is explains why a molded shell wants a level dig and room for a truck.

Slope is ordinary here. The USDA describes the Brackett soils of the Edwards Plateau as benched or stair-stepped, on slopes mostly 1 to 20 percent and as steep as 60 percent. Weathered limestone starts 5 to 20 inches down.

How far from the slope should the pool sit?

The pool should sit far enough back that the ground under its floor is firm and will stay put. For slopes steeper than one foot of fall in three feet of run, the International Building Code calls for foundations in firm material, set back enough for vertical and lateral support. The IBC sets a pool's setback at one-half the footing setback for a building.

Ron Lacher of Pool Engineering, a structural engineering firm for pools, works that out as the height of the slope divided by six. Lacher's article on hillside pools recommends at least 15 feet. The code your city has adopted and your engineer decide the number for your yard.

What holds up the downhill side of the pool?

On a slope, the downhill wall may have to hold the water with no help from the soil. IBC section 1808.7.3 says any part of a pool wall within 7 feet of the top of the slope must support the water without soil support. The trade calls that a freestanding wall, and Lacher recommends building it that way at 10 feet or more.

The reason is weight. Lacher says a pool often holds 200,000 pounds or more of water. If one end settles and the rest does not, the shell tends to crack. The American Shotcrete Association's position statement on pools says a qualified professional engineer must evaluate the structural requirements of a pool shell.

Crew member trowelling fresh gunite on a pool wall
Finishing a gunite wall over its steel at our Olinda Way project. The wall thickness and steel come from the engineering.

What is slope creep?

Slope creep is the slow downhill movement of clay soil as it swells when wet and shrinks when dry. Lacher calls slope creep the most common cause of costly structural distress he sees in hillside pools. He puts the rate at up to 1/4 inch per year and says most soil engineers believe it affects the outer five to eight feet of a slope.

Creep is a clay problem, so a thin cap of soil over limestone is a different site from a yard of clay or builder's fill. A soils report tells you which one you have. GENESIS, the builder education company of the Pool & Hot Tub Alliance, recommends a soils report before any construction begins.

Does a sloped pool need an engineered retaining wall?

Many sloped yards need a retaining wall to make a level deck, and height usually decides whether it must be engineered. The International Residential Code requires an engineered design for an unbraced wall holding back more than 48 inches of unbalanced fill. The threshold drops to 24 inches when the wall resists loads beyond the soil, so ask the engineer whether a deck or pool behind it counts.

Cities add their own rules. Lago Vista's retaining wall guide requires a licensed engineer at 48 inches, and geotechnical testing of the backfill at 72 inches. Austin exempts a wall of 4 feet or less, measured from the bottom of the footing, from a building permit. Austin's exemption ends if the wall supports a surcharge or stands in a flood hazard area.

Where does the stormwater go?

Stormwater from uphill should be carried around the pool and released where it will not wash out the slope below. The rain to plan for is heavy. NOAA raised Austin's 100-year rainfall for 24 hours by as much as three inches, up to 13 inches.

Lacher says surface and subsurface drainage should keep water from ponding near the top of the slope, and that irrigation should neither soak the soil nor let it dry out. Lago Vista's pool permit asks for a landscape plan that shows how the disturbed ground will be stabilized.

Is a negative edge right for a sloped lot?

A descending slope is what makes a negative edge look right, and the catch basin below is where the engineering goes. GENESIS co-founder Skip Phillips, writing in AQUA Magazine, suggests surge capacity equal to 2 inches of the pool's surface area, plus a circulation system for the edge separate from the pool's own.

Wind matters too. Scott Cohen, also in AQUA, warns that water blown past a narrow basin might erode the slope below the pool. On the open lots above Lake Travis where we work as a pool builder in Lago Vista, plan the basin width for wind.

Which permits apply to a pool on a hillside?

A hillside pool can involve the city, the county and the state. Lago Vista requires a form survey when the pool is within 6 feet of a property line, 8 feet of a structure or 28 feet of a septic component. Travis County's land balancing rules, section 482.943, bar cut and fill on slopes over 15 percent unless the design controls erosion with measures such as terraces or diverted runoff.

Over the Edwards Aquifer, TCEQ regulates construction at private homes in the recharge and contributing zones. TCEQ says a homeowner may not need an individual plan if impervious cover stays at or under 20 percent, among other conditions. If a dig on the recharge zone opens a cave or similar feature, work near it stops until TCEQ approves how it will be protected.

What to have ready before a site visit

  • A survey, with topography if you have it, showing easements and setbacks.
  • The location of the septic tank and drain field, if there is one.
  • Any grading or soils report from when the house was built.
  • A photo of where water runs during a hard rain.

Send Trinity Pool Construction the survey and a few photos of the slope, and we will walk the yard with you and show you where a pool fits.

Your backyard

Want this answered for your yard?

Donna and Ben walk the site, draw the design against what is actually there, and put one itemized quote in writing. No sales rep, and the same crew builds it.

Get a quoteCall (512) 999-2460
Keep reading

More notes

Covered outdoor kitchen with a built-in grill and stone counter beside a pool
BuildingAn outdoor kitchen by the pool: what to plan before you build
Blue patio umbrellas shading a tanning ledge with two white in-water loungers at the shallow end of a pool, sheer descents pouring from a stone wall behind
BuildingTanning ledge depth and design: what to decide before you build one
All notes